Construction on the $12 million Boulevard Modernization
Project was scheduled for completion Tuesday, January 21st, but I
see that date has slipped by and the boulevard is nowhere near ready to handle
a full traffic load. Patience, patience we are told; everything will be just
wonderful when it’s done.
Sure, we have dealt with half the road for far longer than
originally thought. Wasn’t the project supposed to be finished last summer? And
set back a bit, weren’t we told it would be ready by the Christmas parade? And
now, with the latest deadline expired we still have the Main Street of the city
clogged with earth moving equipment, barriers, and construction debris.
Initial construction on the project started in April 2013 we
are quickly approaching April 2015, and yet the road is still being worked on.
It is not a particularly long stretch of highway from the McDonald’s at
Westover to the new Courthouse. And yet we are 20 months into construction.
Using Main Street is not a problem for me and perhaps many
others. I simply bypass that section of town, unless I have a specific reason
to go there. When I do, I travel along the back roads to minimize having to
deal with the messed up traffic.
And still there are times when I have to drive on the
segment only to get stopped several times for the light here or there. And play
any one of a number of games as I try to guess which opening will actually
allow me to visit a specific place of business.
For me, and for others like me, it merely becomes a choice.
Do I want to conduct business on that end of town or does the inconvenience
help me make a choice to go elsewhere? Not a problem for me, I go to the
establishments that I have been going to for years. But no doubt all the
waiting has caused some problems for businesses along the corridor.
The city says that there have been legitimate road blocks
during the long and arduous construction process. And to some extent I would
agree. Certainly, our current weather and the weather we had during the late
fall was not conducive to getting the work done.
But I have a longer memory than that. I recall a good
portion of the summer when the back hoes, bull dozers, and bucket loaders
seemed to be parked in the construction areas waiting for someone to show up.
There were days that became weeks when nothing moved and the
weather was delightful. Still, I guess, we ought to understand how one thing
can lead to another. I am sure there are issues somewhere that have helped slow
things down.
Those with businesses along that stretch of highway deserve
praise for their patience. If not for loyal customers one would have to wonder
how they continue to exist. At this point, waiting another month or two
probably won’t put them out of business. But at some point, there has to be an
end.
And yet every end has a beginning. The end of the Boulevard
Project leads directly to the Dupuy Road project. No doubt that will create a
certain amount of confusion along the southern side of Wawa and for Flag Stop
Car Wash. But I suppose at some level they already know what to expect.
Certainly the side street won’t have as detrimental an effect on sales as
clogging up Main Street has had. But then again the city has a lot of lessons
learned from the Boulevard job that probably relate to Dupuy Road. At least,
for me, I still have access from side streets to the east.
No comments:
Post a Comment